8-MW-Cascade set to supply electricity among Dec
The construction work of 8-megawatt-cascade of Rs one.20 billion Himal Dolakha Hydropower Cascade Project in Godak and Ragapani of Ilam Municipality has reached its ending, officers au courant. “The construction work is in a great progess manufacturing electricity among December-end,” Rup Mani Rajbhandari, Chief officer of the Project aforementioned, “The construction of four-kilometer-long canal has all over.” According to the officers, the project can connect the transmission within the national grid through Kabeli passageway. Electricity are made by channeling water from Rajduwali intake into the canal and to powerhouse in Ragapani. “The powerhouse has been equipped with a electrical device together with a switch-yard,” Narendra Chettri, Public Relation Officer of the Project au courant, “We area unit currently acting on a four klick long thirty three kilovolt cable to move electricity.”